The Village Council voted 4-1 on Nov. 10 to deny NuRock's request to waive land and permit fees on two affordable projects. A narrower permit-fee waiver failed for lack of a second.
Overview
The Wellington Village Council voted 4-1 on Nov. 10 to deny fee waivers for two 106-unit affordable apartment projects. The developer, NuRock, will have to pay the village’s fees in full unless it comes back with a new request.
The vote ended a discussion of about 45 minutes on Resolution No. R2026-36, item 9A on the Nov. 10 agenda. The outcome is from the village’s video of the meeting. The village’s Legistar record did not yet list the votes or the minutes on Monday.
The two projects are:
- Residences at Country Grove, 16651 Van Gogh Road
- Residences at Country Landing, 16651 Velazquez Road
Every unit would be affordable, for households earning 30% to 80% of the area median income. Rents would run from $1,130 to $2,178 a month, as our earlier story on the request set out.
What NuRock asked for
The village’s presentation listed the fees for each project. They included $582,406 in village impact fees and $357,800 in payments in place of giving land for parks and civic use. Building permit fees came on top.
At the meeting, NuRock’s representative said the company had narrowed its request after talks with staff. It no longer asked the village to waive its impact fees. It asked for two things:
- a waiver of the payments in place of parks and civic land, which it said the sites of just under 5 acres could not provide
- a waiver of building permit fees, which it estimated at $450,000 and expected to fall when a new state rule on permit fees takes effect Jan. 1
He said NuRock would still pay about $1.5 million in development fees. The company plans to build both projects at the same time, starting in mid to late 2027, he said. Construction would take 12 to 14 months.
How the vote went
Several council members said they supported affordable housing in Wellington but worried about village revenue. They pointed to Amendment 3, which Florida voters approved Nov. 3. It raises the homestead exemption on non-school property taxes to $150,000 in 2027 and $250,000 in 2028.
One council member said the timing was wrong. The village should see how Amendment 3 affects its budget before it waives fees for anyone, the member said.
Another member moved a middle path: waive only the building permit fees. Those fees stay in the building department’s own fund and cannot pay for other village services, the council heard. That motion died for lack of a second.
A motion to deny the waiver request then passed 4-1. The video does not make clear who cast the vote against.
Two residents spoke against the waivers during public comment. One said the waived fees would fall on other taxpayers. The other objected to waiving the parks and civic land requirement.
What it means for you
The vote does not stop the apartments. Under the state’s Live Local Act, projects like these are approved by village staff, not the council. The question on Nov. 10 was only who pays the fees that fund roads, parks and public buildings for new residents.
For now, that is NuRock. Palm Beach County has already picked both projects for low-interest loans from its housing bond program, the developer said. The county is also covering part of its own impact fees, the village’s presentation shows.
The full fee tables are in the village’s fee waiver presentation for Nov. 10.